DoIT Operational Framework - Section 3.3 - Change Request Standards
Navigate back to DoIT Operational Framework - Section 3.0 - Change Management (section overview)
3.3.1 Defining Change Levels
Impact and Risk determine the Change Level.
| Table 3.1 - Change Levels |
Risk |
Low |
Medium |
High |
Impact (Users Affected) |
High (campus or department) |
Level 2 Change |
Level 1 Change |
Level 1 Change |
Medium (group) |
Level 3 Change |
Level 2 Change |
Level 1 Change |
Low (person) |
Level 3 Change |
Level 3 Change |
Level 2 Change |
Risk is a combination of three factors:
- Change Complexity – Is the Change complicated, average or simple?
- Change Interdependency – Is the Change dependent on many other Changes, a few other Changes, or is it a simple and independent Change?
- Implementation Experience – Does the organization have proven, limited or no experience with this Change?
Determination of Risk
- If either the Change Complexity or Change Interdependency is complicated, or we have no experience with this type of change, then the Risk is High.
- If either the Change Complexity or Change Interdependency is average, or we have limited experience with this type of change, then the Scheduling Risk is Medium.
- Otherwise, the Risk is Low.
3.3.2 Levels of Changes and Required Approvals
Level 1 Changes
- Public Notification – 4 weeks notice on the DoIT Outage Page after Change Approval. See DoIT Operational Framework 3.6 - Customer Notification.
- Time – During Standard, Pre-Established Maintenance Window Desired, or Alternate with Approval.
- Submission – No less than 2 business days prior to required approval date.
- Approval – Change Manager → SEO Director → DoIT Tech Directors.
- Management – Implementation Manager, in active contact, with Escalation Plan in place.
Level 2 Changes
- Public Notification – 2 weeks notice on the DoIT Outage Page after Change Approval. See DoIT Operational Framework 3.6 - Customer Notification.
- Time – During Standard, Pre-Established Maintenance Window Desired, or Alternate with Approval.
- Submission – No less than 2 business days prior to required approval date.
- Approval – Change Manager → SEO Director (Tech Directors Optional).
- Management – Implementation Manager reachable with Escalation Plan understood.
Level 3 Changes
- Public Notification – Service Manager or Team discretion.
- Time – During Standard, Pre-Established Maintenance Window.
- Submission – No less than 2 business days prior to required approval date.
- Approval – Change Manager.
- Management – Technologist available.
Emergency Changes
- Public Notification – Immediate Notice as possible.
- Time – Immediate.
- Submission – Retroactive possible; Otherwise, Immediate as situation permits.
- Approval – Retroactive possible; Otherwise, Change Manager → SEO Director → DoIT Tech Directors.
- Management – As immediately necessary; Implementation or Situation Manager onsite.
3.3.3 Approval Standards for Change Requests
3.3.3.1 Non-Emergency Change Request
Level 1 Changes
Change has been tested; a formal escalation and back-out plan is available; an implementation manager has been designated; and 4 weeks are available for public notification.
Level 2 Changes
Change has been tested, or DoIT has experience with this change; an escalation and back-out plan is understood; an implementation manager has been designated; and 2 weeks are available for public notification.
Level 3 Changes
Required information has been entered in the CR.
3.3.3.2 Emergency Changes
An appropriate DoIT manager or director must approve emergency changes prior to implementation. NOC must also be notified as soon as possible of emergency changes. Emergency Change Requests are expedited in the following ways:
- The time required to process the Change Request is shorter.
- The method of notifying people affiliated with the Change Request is switched from circumstance to circumstance and may include personal contact.
- The DoIT Change Manager may call a special review meeting.
- The DoIT Change Manager, in conjunction with senior DoIT and customer management may choose to waive or postpone standard requirements for moving a Change Request into production.
- All emergency and service changes that impact the normal business operation (including weekends) requires that all DoIT Management and Campus Users be notified of the disruption. This includes the scope and duration of the change.
It is the responsibility of the person/team performing the change to ensure that approval has been granted.
The DoIT Change Manager is responsible for noting all commitments and conflicts. It is possible for change activities associated with an Emergency Change Request to pre-empt other scheduled changes.
| Keywords: | Defining Change Types Type of Change Risk Types of Changes and Required Approvals Approval Standards for Change Requests Non-Emergency Change Request Emergency Changes | Doc ID: | 8933 |
|---|
| Owner: | Hans W. | Group: | Systems & Network Control Center |
|---|
| Created: | 2009-01-28 | Updated: | 2009-11-18 |
|---|