MyUW Roadmap
MyUW Legacy Roadmap
Milestone |
Quarter |
Status |
|---|---|---|
|
Maintaining service operations Working with UW Forward team on transition timeline Evaluating content (Identifying stale applications) |
FY 26 Q2 through FY27 |
In progress |
|
Communicating changes with Campus partners through Fall lunch and learn sessions |
FY26 Q2 |
Completed |
|
Ongoing communications with Campus partners |
FY27- Q1, Q2 |
Not yet started |
|
Systematically sunset the current uPortal infrastructure, migrate remaining applications, handle data compliance |
FY27- Q2, Q3 |
Not yet started |
MyUW Forward Project
The MyUW Forward Project will migrate MyUW to Salesforce Experience Cloud—preserving the features you’re used to while unlocking opportunities for new innovations, faster development and better personalization. Learn more about the MyUW Forward Project.
Milestone |
Quarter |
Status |
|---|---|---|
|
Develop standard MyUW tiles |
FY26 Q2 |
Completed |
|
Hold Lunch & Learn Sessions about MyUW Forward for Tile Stakeholders |
FY26 Q2 |
Completed |
|
Build core functionality in the Salesforce Experience Cloud Platform |
FY26 Q2-Q3 |
Completed |
|
Refine search and layout, internal quality assurance |
FY26 Q3-Q4 |
In Progress |
|
User Testing, New Features, Campus Communications |
FY27 Q1 |
Not started |
|
Prepare for Soft Launch |
FY27 Q2 |
Not started |
|
Soft Launch Period: Phased rollout of new MyUW experience availability for select user groups, gather user feedback for rapid improvements, complete application migrations |
FY27 Q2 - Q4 |
Not started |
|
Transition from project mode to standard service operations model |
FY27 Q4 |
Not started |
|
Launch new MyUW experience for all users, continue development based on user feedback, begin to sunset previous platform infrastructure |
FY27 Q4 |
Not started |