ECMS - 14 August 2020 Patch Timeline

This document provides an outline of important dates related to the 14 August 2020 upgrade of Perceptive Content.

  • July 6 - August 21: New work/Onboarding work freeze
  • July 16 - The test environment will be available for testing.
  • August 7: Final day to submit testing results. To submit results, please use the Testing Report/Issue Form
  • August 13-14: The patch is implemented into production. Production ImageNow will be available during business hours. Patching will start at 6:00p.m. and should finish later in the evening.
  • August 14: Post-patch testing.
    • Please ensure that your business processes still function as expected after the patch is implemented into production. Please submit your test results using the Testing Report/Issue Form before 11:00a.m. If necessary, the decision to rollback the patch will be made at Noon.
    • When we successfully conclude acceptance testing, we will increment the PEDS service and clients configured for PEDS will begin to update when they are launched (using the Desktop shortcut or the Windows Tray icon). If you use PEDS to update clients, please tell your staff to be patient and allow the update to conclude without interruption. If your staff need to access documents on the Imaging system before they have the correct version of the client on their workstation, they can use Perceptive Experience (https://imaging.wisc.edu/perceptiveexperience/).

See Also:




Keywords:ecms upgrade August 2020 testing days schedule dates time reporting imagenow perceptive content   Doc ID:74279
Owner:CRAIG S.Group:ECMS
Created:2017-06-23 09:58 CDTUpdated:2020-06-30 06:55 CDT
Sites:DoIT Help Desk, ECMS
Feedback:  0   0